TxDOT Update Week of March 31
(Post sponsored by Tinsley Title, Holt Wrecker, R&R lawn specialists, Gibson Pharmacy.)
Athens crews are scheduled to perform mill and inlay on FM 3079. Expect lane closures with flaggers controlling traffic. Also, crews are scheduled to perform street sweeping, sign maintenance, and herbicide application at various locations throughout the county.
Henderson County construction projects updates:
SH 198 Bridge Project
Limits: At the Clear Creek Bridge a mile north of FM 3054 to 0.1 mile north of CR 2830
Contractor: Copasa Inc.
Cost: $30.4 million
Anticipated Completion Date: Major items of work have been completed.
The contractor is awaiting final acceptance. The project includes replacing bridges and approaches, grading, structures, base and surface work, retaining walls, curbs and gutters, fencing, and striping.
FM 316 Rehabilitation
Limits: From FM 1861 to US 175
Contractor: Baker & Company Construction, LLC
Cost: $7.9 million
Anticipated Completion Date: Major items of work have been completed.
The project is in time suspension and awaiting final acceptance. The project includes pavement reconstruction, structures, pavement markings and signs.
FM 315 Rehabilitation
Limits: From FM 3079 to FM 317
Contractor: Big Creek Construction, LTD
Cost: $1.9 million
Anticipated Completion Date: Major items of work have been completed.
The contractor is awaiting final acceptance. No work is scheduled this week. The project includes pavement reconstruction, structures, pavement markings and signs.
BUS 19 Sidewalks
Limits: From Ben Belt Fr. To S Loop 7 ramps
Contractor: 3LW Civil, LCC
Cost: $2.6 million
Anticipated Completion Date: Summer 2025
The contractor is placing concrete for the sidewalks and driveways. Motorists should expect lane closures while work is in progress. This project includes sidewalk and pedestrian lane improvements.
SH 19 Super 2 Project
Limits: From 0.3 Mi. S of FM 1861 (Van Zandt C/L) S to 0.1 Mi. N of SL 7 in Athens (Watson)
Contractor: Big Creek Construction LTD
Cost: $20.8 million
The contractor is scheduled to work on driveway pipes and ditch grading. The speed limit is reduced to 60 mph throughout the project limits. This project includes adding a passing lane in each direction at multiple locations. It also includes grading, drainage structures, pavement markings, and signage.